Just Completed Portacabin For French International School Lagos Nigeria
Casting of Portacabin Plinth In Progress
Off Site Fabrication Of Portacabin Base, Anti-rust Treatment For All Steel Members, And Assembling Steel Base Onsite
Installation Of Panels
Installation Of Marine Board, Installation Of Ceiling Panel, Laying Of Tiles, Electrical First Fix, Window, Facial Cladding
Window Final Fix, Light Fittings, AC, Shelves, Temporary Cleaning
Roof Gutter Pipe Connections To The Existing Drainage System
Job Completed And Delivered