Just Completed Portacabin For French International School Lagos Nigeria

Casting of Portacabin Plinth In Progress

Off Site Fabrication Of Portacabin Base, Anti-rust Treatment For All Steel Members, And Assembling Steel Base Onsite

Installation Of Panels

Installation Of Marine Board, Installation Of Ceiling Panel, Laying Of Tiles, Electrical First Fix, Window, Facial Cladding

Window Final Fix, Light Fittings, AC, Shelves, Temporary Cleaning

Roof Gutter Pipe Connections To The Existing Drainage System

Job Completed And Delivered